New Student Offer Use Code - HELLO

Join Here

Time and Work Formulas

Published on Friday, December 15, 2017

Work

Amount of job assigned or the amount of job actually done.

Relations between work, time and person: -

  • Work & Person: Directly proportional i.e. more work, more person required. 
  • Time & Person: Inversely proportional i.e. more people, less time required. 
  • Work & time: Directly proportional i.e. more work, more time required. 

Note:
Work done is always considered to be equal to 1.

Rules: -

  • If a person can do a piece of work in ‘n’ days/ hours then that person’s one day’s/ hour’s work = 1/n
  • If a person’s one day’s/ hour’s work = 1/, then he will complete then he will complete the work in ‘n’ days/ hours. 
  • If first person is ‘n’ times efficient than second person then work done by first person : second person = n : 1 
  • If the ratio of number of men required to complete a work is m : n then the ratio of time taken by them will be n : m. 

Time and Work - Shortcuts and Tricks

Formulas Including Short Tricks:

# 1.

 If persons can do W1 work in D1 days working T1 hours in a day and M2 Persons can do W2 work in D2 days working T2 hours in a day then the relationship between them is
Example: - 12 persons can make 20 toys in 10 days working 12 hours a day. Then in how many days can 24 persons make 32 toys working 16 hours a day?

# 2.

If A can do a piece of work in days and B can do the same work in days then (A + B)’s one day work-
Time taken by (A + B) to complete the work –
If ‘n’ persons (more than two) are there then their one day’s work =
Where x1,x2, x3 …………… represents the number of days taken by them to complete the work.

Example: -  If A can do a piece of work in days and B can do the same work in days. If both are working together, how many days will they take to complete the work?
(A + B)’s one day work =
(A + B) will complete the whole work =

# 3.

If A & B can complete a work in days and A alone can finish that work in days then number of days required by B to complete the work–
Example: - A & B together can do a piece of work in days and A alone can do it in 18 days. In how many days can B alone do it?

# 4.

If A & B can do a piece of work in days, B & C can the same work in days and A & C can do it in days, then working together A,B & C can do that work in–
Example: -  A & B can do a piece of work in days, B & C can the same work in 9 days and A & C can do it in days, then find the time in which A, B & C can finish the work if they working together?

# 5.

If A can do a work in days and B can do faster than A, then B will complete the work in -
Example: - Komal can do a work in days and Pooja is more efficient than Komal to complete the same work, then find the total time taken to complete the work by Pooja?

# 6.

If A takes days more to complete a work than the time taken by (A + B) to do the same work and B takes y days more than the time taken by (A + B) to do the same work then (A + B) do the work in √xy days –
Example: -  If A alone does a piece of work, he takes days more than the time taken by (A + B) to do complete the work, while B alone takes 9 days more than the time taken by (A + B) to finish the work. What time A & B together will take to finish the work?

# 7.

If A & B each alone can do a piece of work in days respectively. Both begin together but –
I. A leaves the work ’n’ days before its completion, then total time taken for completion of work :
II. B leaves the work ’n’ days before its completion, then total time taken for completion of work :
Example: - A can do a piece of work in days while B can do it in days. They begin together but 5 days before the completion of the work, B leaves off. Find the total number of days for the work to be completed?

# 8.

If A & B do a piece of work in days respectively. Both begin together but after some days, A leaves off & the remaining work is completed by B in ‘n’ days. Then the time after which A left, is given by 
Example: - A & B do a piece of work in days respectively. Both begin together but after a certain time, A leaves off. In this case, B finishes the remaining work in 20 days. After how many days did A leave?


ebook store

About Me

Ramandeep Singh

Ramandeep Singh - Educator

I'm Ramandeep Singh, your guide to banking and insurance exams. With 14 years of experience and over 5000 successful selections, I understand the path to success firsthand, having transitioned from Dena Bank and SBI. I'm passionate about helping you achieve your banking and insurance dreams.

  • Follow me:
Close Menu
Close Menu